
Jan 21, 2010

Jan 27, 2010
More Pictures in the Photo Gallery
CONSTRUCTION UPDATE:
The following represents construction progress for the week ending February 28, 2010:
Meetings held over the last week included:
- The weekly owner/architect/contractor meeting.
- A meeting with Cator Ruma to discuss the bid returns for the low voltage wiring contract.
- A meeting with the landscape contractor to discuss phasing of the irrigation systems
- A meeting with SAUMC staff and Fransen Pittman to formulate plans for expansion of the trash castle.
Thank you,
Keith Winkel
For your Building Committee
The following represents construction progress for the week ending February 21, 2010:
The latest schedule from Fransen Pittman shows completion of the project on October 7, 2010.
Meetings held over the last week included:
- The weekly owner/architect/contractor meeting.
- A site visit to Rocky Mountain Prestress to inspect the precast columns.
- Interior Design Subcommittee meeting to discuss the pews for the sanctuary.
- A site visit and meeting with FirstBank to discuss the monthly pay draw.
- Columbarium Task Force organizational meeting.
- Cator Ruma to discuss the security system request for proposal.
- SlaterPaull and SMW to discuss the vendors proposals for the audio/visual system.
Thank you.
Keith Winkel
For your Building Committee
The following represents construction progress for the week ending February 14, 2010.
Meetings held over the last week included:
- The weekly owner/architect/contractor meeting.
- Meeting with Panasonic, the audio/visual designer, SlaterPaull and SAUMC for a demonstration of the projection system for the sanctuary.
Thank you.
Keith Winkel
For your Building Committee
The following represents construction progress for the week ending February 7, 2010:
Meetings held over the last week include:
- The weekly owner/architect/contractor meeting.
- Technology Subcommittee meeting to discuss IT requirements
- A meeting between SlaterPaull, SAUMC and Church Organs of Colorado to review and discuss the final design of the organ façade.
Thank you.
Keith Winkel
For your Building Committee
The following represents construction progress for the week ending January 31, 2010.
Thank you.
Keith Winkel
for your Building Committee
- Completed setting forms, placing reinforcing steel and installing embedded metal for the sanctuary east foundation walls.
- Placed concrete for the sanctuary east foundation walls on Tuesday.
- Started removing forms from the sanctuary east foundation walls on Saturday.
- Completed setting forms, placing reinforcing steel and installing embedded metal for the link building west, east and north foundation walls.
- Placed concrete for the link building west, east and north foundation walls on Thursday.
- Completed setting forms and placing reinforcing steel for the pier caps in the sanctuary building.
- Laid out survey control points for the sanctuary south foundation wall. Setting forms and placing reinforcing steel will start next week.
- Continued the installation of electrical conduit from the existing electrical room to the new buildings.
- Performed maintenance on the temporary erosion control facilities.
- Graded for the new sidewalk from the south entrance of the existing building to the southwest car park. Placed concrete for this sidewalk on Friday.
- About 40 feet of curb and gutter at the north end of the new car park pulled away from the asphalt and partially collapsed due to ground water in the area. Installed a minor drainage system and replaced the curb and gutter on Friday.
- Received the State of Colorado permit to discharge our ground water drainage system into the storm sewers. We will make the connection from the two drainage systems to the storm sewer the week of January 25.
Meeting hold over the last week included:
- The weekly owner/architect/contractor meeting.
- Building Committee meeting.
- SAUMC/SlaterPaull/Fransen Pittman meeting to discuss the exclusions and clarifications to the revised GMP.
- Meeting with FirstBank to review the monthly draw sheet and conduct a tour of the site.
- Meeting with Cator Ruma to discuss the bid package for the low voltage wiring installation.
- Attended the Church Council meeting to discuss the design and construction of a potential columbarium.
- Conducted a site visit along with the Interior Design Subcommittee chairperson to review the progress and workmanship of the precast columns at Rocky Mountain Prestress.
Thank you.
Keith Winkel
For your Building Committee
Meetings held over the last week included:
- Commissioning meeting with Bradshaw Building Solutions to discuss the mechanical commissioning scope of work.
- Meeting with Burton Technologies to discuss the installation of IT equipment in the new facility.
- The owner/architect/contractor meeting held each Tuesday morning.
- Meeting with SlaterPaull and Church Organs of Colorado to discuss installation details for the new organ.
- Interior Design Subcommittee meeting to discuss the selection of pews and chairs for the sanctuary.
- Meeting with Security Central to discuss the installation of security equipment in the new facility.
- Prayer Subcommittee meeting to finalize plans for the first on-site prayer gathering on January 9.
- Meeting with BT Communications to discuss the installation of telephone equipment in the new facility.
- Prayer gathering on Saturday morning to place a prayer box in the building foundation under the chancel.
Thank you,
Keith Winkel
For your Building Committee
January 19, 2010 Meeting Notes BCMinutes011910
November 24, 2009 Meeting Notes BCMinutes112409
October 27, 2009 Meeting Notes BCMinutes102709
September 29, 2009 Meeting Notes BCMinutes092909
September 22, 2009 Meeting Notes BCMinutes092209
September 15, 2009 Meeting Notes BCMinutes091509
September 1, 2009 Meeting Notes BCMinutes090109
August 18, 2009 Meeting Notes BCMinutes081809
August 4, 2009 Meeting Notes BCMinutes080409.pdf
July 4, 2009 Reduce, Reuse, and Recycle SAUMCReduceReuseRecycle070409.doc_.pdf
June 10, 2009 DD Energy Summary DDEnergySummary_06-09-09.pdf
May 12, 2009 Meeting Notes >BCMinutes5-12-09.pdf
May 5, 2009 Meeting Notes >BCMinutes5-05-09.pdf
April 28, 2009 Meeting Notes >BCMinutes4-28-09.pdf
April 14, 2009 Meeting Notes >BCMinutes4-14-09.pdf
April 7, 2009 Meeting Notes >BCMinutes4-7-09.pdf
March 17, 2009 Meeting Notes >BCNotes3-17-09a.pdf
January 28, 2009 Sustainability Principles >SustainabilityPrinciplesasof090128.pdf
We have almost completed the Schematic Design Phase and will have a church-wide vote on February 22nd to approve beginning the Design Development stage.
Drawings produced during the Schematic Design Phase provided the site configuration and “look” of the exterior of the building which were both needed for the Site Improvement Plan (SIP) submitted to Douglas County. The Design Development stage will further develop the layout of the interior space and provide more detail to the schematic drawings. From the design drawings our general contractor will be able to obtain bids from subcontractors and give us a “guaranteed maximum price” (GMP) bid for construction. The design drawings also will allow us to negotiate a firm commitment from lenders to finance the project.
For the most part, yes. We are still planning on:
Approximately $12 million total cost
26,100 additional square feet of finished space on two levels - balanced between all of our needs for space, including, but not limited to: worship, children, youth, adult, outreach, music and the arts, fellowship, administration, storage, etc. This will include approximately 1,000 worship seats (including the choir) in a separate sanctuary while also keeping an eye on future phases to complete the Master Plan.
Upgraded/expanded parking
12,400 square feet of unfinished space under the new sanctuary. Although it would be ideal to finish this space as soon as possible, the additional $800,000 + to do so is not within the $12 million budget. We may find, as we did with the build out of the “West Wing” shortly after moving to the current building, that this “mini-project” may occur before subsequent phases.
We have made information and drawings from the Schematic Design Phase available to the congregation since early January. The architects made a presentation on Sunday, February 8th. The Building Committee has kept Leadership Council and staff up-to-date with the plans. Leadership Council has endorsed the Committee’s recommendation for a Church Conference on February 22nd at which time there will be discussion of the plans and a vote whether or not to proceed with Design Development. If the church approves proceeding: i) design drawings will be prepared, ii) a GMP (see A2 above) obtained, and iii) a financing proposal submitted – all for another Church Conference vote. If approved, construction drawings would be prepared, commitments would be made to contractors and lenders and construction would proceed.
This becomes a three-part question. First, from a ministry perspective. The need for each of our ministry programs is greater than ever. Our worship attendance, Sunday School attendance and participation in adult education and congregational care classes all increased in 2008 over 2007. Our need to accommodate more people looking to the church for spiritual guidance and direction is as great as it has been.
Second, from a construction perspective. It is an opportune and advantageous time to move ahead with our project. Steel prices, fuel costs and material costs have fallen dramatically. Also, our general contractor’s subcontractors are anxious for work and indicating they will be very aggressive in their bids.
Third, from an overall economy perspective. Will the effects of the economic downturn on our members allow them to pay their capital budget pledges? We are concerned about this, but our active, committed congregation has shown time and again they come through in rough times. We do need to remain conscious of this, however, and remain sensitive to the challenges confronting our members. Discussions and votes in our church conferences will reflect what we, as a church family, should do from both project scope and schedule perspectives.
As members of the St. Andrew congregation, the Building Committee members have struggled with this issue. While we believe that expanding our building campus would present opportunities to reach more people and grow our ministries, we have to balance that with the needs of our existing ministry areas as well. Ultimately, the decision to build Phase II is the decision of the church as a whole – not the Building Committee nor Leadership Council. Thus far, the church members have voiced their approval for the project through their pledges and through their vote at previous church conferences.
The church conference on February 22nd is simply to decide whether to proceed with the Design Development stage – not to sign a contract to start construction. That decision will be for a later church conference – in May or early June. At that time we will have more information regarding pledge collections, construction costs, financing options, etc. Members will have an opportunity at that time to vote to go forward or “mothball” the project.
The capital funds received from the Live Our Vision campaign were designated by the donors to be applied to Phase II. We are obligated to use those funds for the intended purpose. Consistent with those directions, architectural and other professional fees (approved by church vote) have been paid to complete the Study and Schematic Design Phases. If church donors decide to redirect future pledges toward the operating fund, that is their choice and not within the church’s discretion.
If the church approves going forward with Design Development, up to $475,000 would be spent toward the completion of the design drawings. (These costs are included in the anticipated $12 million total project cost). If the church votes at a subsequent church conference not to proceed with construction in 2009, the design drawings can still be used at a later time to generate construction drawing when construction does begin. We believe the tissue is not if Phase II will occur but when.
Our master plan has changed somewhat from the model. The model was based on the Master Plan developed more than eight years ago. Much work and many considerations went into revising the Master Plan. The model did not reflect those changes, and we believed it caused too much confusion so we removed it. The pictures currently shown by the elevator and across from the Chapel accurately reflect our current plan.
We are doing everything we can to make our new addition environmentally friendly and sustainable. The project has been designed to be certified; however, we do not envision paying the fees required to obtain LEED certification. From building processes, to using environmentally sensitive building materials, to using low-water xeriscape landscaping, to minimizing artificial lighting during daytime use, to putting in the most efficient HVAC (Heating, Ventilation and Air Conditioning) system, we’re following LEED criteria.
Current plans call for a sloped floor, a center aisle and a combination of pews and chairs. There will probably be a significant level floor area in front of the chancel so we can accommodate various functions, including concerts. Therefore, the sloped floor won’t extend right up to the chancel area. Seating in that area will need to be flexible to accommodate various functions, so this seating will probably be moveable chairs.
The top of the current sanctuary is about thirty-three feet above the main floor. The top of the new sanctuary will be about forty-eight feet above the main floor.
YES!!! This is one lesson we’ve learned from our current space. We will be able to control the amount of sunlight coming into the new sanctuary. The precise design details will be worked out in Design Development.
Because of cost concerns for Phase II, the lower level of the sanctuary building will be totally unused and unfinished except for two mechanical areas. This may even mean a dirt floor until it is finished in future phases.
Yes. While a full kitchen is planned in the full Master Plan, Phase II will see the current upper-level kitchen expanded at its current location, and the county will allow us to have cook tops. The lower-level Children’s and Youth kitchens will likely be retained.
Phase II currently includes our labyrinth near the corner of White Bay and Viaggio Way and the beginnings of the Memorial Walk. However, because of costs, the final Memorial Walk and Columbarium will probably be completed in future phases.
Yes. The ventilation system we’re planning for the sanctuary will make a scent-free zone very doable. The air flow will be markedly different from our current sanctuary because our current sanctuary was planned as a multi-use space with its associated ventilation system. The architects has allocated some space in the sanctuary that will be enclosed as “scent-free” and will be located in close proximity to an exit.
The Building Committee, architects, staff and ministry leaders have had many discussions concerning how the current sanctuary, as well as the current building, will be used. The current worship space was originally designed to be “multi-purpose” so once the “permanent” sanctuary was built in Phase II, this space could be used for various activities. How this space will be used upon the completion of Phase II will be determined during Design Development.
An estimated increase of $350,000 in annual costs would be associated with the additional physical space. Assuming attendance would increase, we would also need to address increased ministry costs. Presumably, more attendance would result in more revenue to offset those costs.
If the church supports the project through its vote at the February 22nd church conference and at the conference vote anticipated in the spring, construction will probably start during the Fall of 2009, and we hope to move in during the Fall of 2010.
Our current mortgage balance is about $2.3 million with a monthly payment of $33,771. To put this in perspective, we’ve only been in our building 4 years. It cost about $16.5 million so we’re making remarkable progress paying it off!! Additionally, we have a current cash balance of about $380,000 of Follow The Vision capital funds to further satisfy the existing debt service payments. And we have collected more than $1.2 million of Live Our Vision capital funds.
We will obtain a construction loan for Phase II and when Phase II is completed, we’ll obtain long-term financing that will include the Phase II construction balance and our current loan.
Please go to our church’s web site, St-Andrew-umc.com for more information. Also, you may visit with Building Committee representatives located at the main entrance and across from the chapel on Sunday mornings. Drawings are on display at those locations throughout the week.
Please feel free to talk with the members of our Building Committee. They are:
Chairmen
Members
Our groundbreaking service was wonderful, and we're set to start construction. We'll see fences and large machines on site starting approximately Sep 15. Once work is underway, we will need to adjust our parking habits for approximately 5 to 6 weeks. During this time our General Contractor, Fransen Pittman, will be building the new parking lot where the gravel lot is now—which will necessitate reducing our current upper parking to about half of what it is now. This will be short-term pain for long-term gain. When the new parking lot is done, there will be more paved parking available than ever before!!
In the interim, we suggest folks ride the shuttle buses from the two bank lots (US Bank and 1STBank) south of the church on University. We'll be increasing the shuttle frequencies during this time frame while continuing to serve the Hyatt Classic Residences and WindCrest. Please DO NOT park in the Urgent Care or medical lots near US Bank or by Marshall’s and Staples near 1STBank.
There will be a limited amount of parking in the church lots. Watch for our friendly parking attendants who will be on hand to assist you as well as new directional signs and fences.
The ‘youth’ parking lot by the playground will be reserved for handicapped parking, visitors and people with mobility needs including older adults, pregnant women and others with special needs. However, if that lot does not fill up before each service, parking attendants have the discretion of allowing other cars to park there.
There is to be NO PARKING on White Bay Drive between University and our entrance, going either direction. This facilitates overall traffic flow by allowing two lanes of traffic and emergency vehicle traffic if needed. If you park on the streets of Tresana, please be safe, legal and a good neighbor!!!
We ask for your patience during this process. It WILL get better before you know it. And, the excitement of our expanded facility will make it all worth while.
Please feel free to e-mail me at (JavaScript must be enabled to view this email address) with your comments or suggestions!!!
Thank you.
Keith Winkel
for your Building Committee
The Building Committee has been making great progress in the Design Phase of our facilities expansion program. The overall site plan has been finalized. The foot print of the new sanctuary and the connection building are almost set and work has begun on the interior configuration of the new building and the modifications that will be needed in our existing building. However, while a great deal of work has been completed there are still a lot of details to be worked out before the final design will be ready to be brought before a church conference for a vote of approval.
As a result of many meetings, discussions and continuous refinement, there have been some changes to the model we’ve all been looking at for the last seven years. The changes have evolved from intensive discussion about how to build a facility to service our ministry needs while remaining true to our call to be good stewards of our financial resources. And at the same time have as little environmental impact as possible, both in the initial construction of the new facilities and in the future operation of the building. In addition to addressing ministry needs, good stewardship and environmental impact, significant thought is also being given to how to provide for cost effective future expansions with minimal impact on the then existing operations of the church.
While charged with developing the design, the Building Committee is also giving significant consideration to the economic environment we currently find ourselves in. Balancing our ministry needs, both today and in the future, with our commitment as a congregation to remain financially sound is a primary objective. Our potential construction lenders remain optimistic and committed to St. Andrew and this project. While it is not possible at this time to know exactly where the financial markets will be at the time we will need to borrow funds, the Building Committee is working with the Finance Committee and a comprehensive financial plan will be part of the Design Phase recommendation when presented to the church conference for approval.
The current schedule has also changed a little from what has previously been communicated. The Building Committee is now anticipating that the Design Phase will be completed by mid-February, 2009 and the church conference held sometime shortly thereafter. If the church membership approves going forward with the expansion, we should be ready to break ground sometime in the summer of 2009. While the actual ground breaking is a few months later than originally anticipated, design changes have resulted in a shortened projected construction duration so it is still expected that the new facilities will be ready for occupancy in late 2010.
The new site plan, building foot print and preliminary exterior elevations are on display by the new monitor inside the front door and everyone is encouraged to stop by and take a look. Members of the Building Committee will be at the display between most worship services to answer questions and hear your feedback. In addition, as more details are developed they will be on display in Room 252. Please stop by to keep abreast of this important step in the continuing growth of St. Andrew.
The Building Committee was commissioned by a Charge Conference on June 21, 2007.
The initial objective was to undertake a “Study Phase” to determine the scope of the next building phase.
The committee was comprised of clergy (2), staff (5) and laity (9).
The committee met over 20 times between August, 2007 and June, 2008.
The Building Committee’s consultants interviewed staff and laity about worship, music and the arts, children’s, youth and adult education, fellowship, facilities, administration, outreach and congregational care.
Minutes from each committee meeting were forwarded to Leadership Council.
Members of the Building Committee were present at the model during worship service for 2 months to receive input/answer questions from the congregation.
Three congregational Q&A sessions were held to receive input and answer questions from the congregation.
The primary focus of any expansion is to provide for SAUMC’s future ministry needs.
Attendance at worship service is the most common way families / individuals are introduced to a new church.
If a church parking lot is full, newer worshippers will not expend the effort to find a parking place and attend.
A sanctuary that is 85% full appears to be at capacity to a new attendee.
46% of the families in SAUMC’s immediate area have no church affiliation.
Worship services at the most popular times are nearing capacity and at our current growth rates will exceed capacity before an expansion can be completed.
Sunday school at the most popular time (9:40) is at capacity.
We have reached capacity in most areas of SAUMC’s existing ministry due to space constraints.
The Building Committee considered expansion alternatives of $6, $9 and $12 million.
The $6 and $9 million options:
The $12 million option, while certainly the most ambitious:
The recent capital campaign received 580 pledges, totaling approximately $7,850,000. 580 pledges is 110 more than the prior capital campaign.
$7,850,000 is more than double what has been pledged in any previous capital campaign.
Our bankers consider the results of the capital campaign truly inspiring given the current economy.
The outstanding balance on the existing mortgage is projected to be $1,958,000 at the end of its term (May, 2010).
The proposed $12 million expansion will require $5,257,000 of new debt.
The total debt (existing + new) at the conclusion of construction is projected to be $7,215,000.
Lenders are willing to lend SAUMC almost double the $7,215,000 being contemplated, which would allow for an even larger expansion, but the Building Committee does not feel that would be fiscally responsible.
Given current capital market conditions, the payments on a 10 year term will be approximately $1 million annually.
A $1,000,000 annual payment is consistent with SAUMC’s average annual capital pledge for the last nine years.
All financial considerations are currently being evaluated by the Finance Committee, including a survey of other large churches.
Church Conference
A church conference will be held on July 27th at 12:15 to consider approving $400,000 of the Live Our Vision capital campaign pledges to fund the cost of continuing through the Schematic Design Phase. The $400,000 is included in the $12 million estimated cost.
In the Schematic Design Phase specific design details and more exact cost estimates will be developed.
A subsequent church conference late this year or early in 2009 will be held to approve the results of the Schematic Design Phase before commencing with any construction or securing any additional financing.
Members of the Building Committee will be present at the model between worship services on each of the next 4 Sundays to receive input/answer questions.
As expected with any undertaking of this scope, there are still some outstanding questions and reservations. The Building Committee will meet on July 22nd at 6:30 and encourages all those with questions and reservations to please plan to attend the meeting and make their thoughts and feelings known so that the ultimate committee recommendations reflect a true consensus of the congregation of St. Andrew. The Building Committee also wishes to sincerely thank the congregation for its overwhelming support as we continue on our mission to:
INVITE, RECEIVE, NURTURE, CHALLENGE AND SEND FORTH COMMITTED CHRISTIAN DISCIPLES.
Respectfully in Christ, The Building Committee Allen Amis & Brad McNealy ~ Building Committee Co-Chairs